Spring 2003 (11.1)
Pages
68-71
New Drilling Rig
Exxon
Azerbaijan to Inaugurate New Oil Rig
Photos: The new drilling rig, currently known
as DSS-20, which is currently being assembled at the Baku shipyard.
This rig will be able to drill in greater depths of water than
any existing rig in the Caspian.
A new drilling rig known
as DSS-20 owned by Maersk Contractors is currently being assembled
at the Baku shipyard. Once it's finished, the semi-submersible
rig will be the largest and most powerful drilling unit in the
Caspian Sea, capable of operating in water depths of up to one
kilometer and drilling to depths of more than nine km. The DSS-20
is being built by KeppelFELS; but both ExxonMobil and ChevronTexaco
have made significant investments in its construction.
Currently, there are three other rigs available for offshore
drilling in Azerbaijan: Istiglal, which can drill deepwater structures,
and Dada Gorgud and Qurtulush, which both drill in shallow water.
DSS-20 will be able to drill in even greater water depths than
Istiglal. The construction of this new rig was driven by the
need to improve the drilling infrastructure and to help meet
drilling needs for deepwater areas in the Caspian. The DSS-20
will accommodate as many as 130 persons on board and will meet
full international regulatory requirements.
Construction of pontoons, columns, and
drill floor components was completed in Singapore; in the summer
of 2002, these components were transported to the Baku shipyard
safely and without any incidents.
Since then, the rig hull has been completed, the drill floor
has been erected, and assembly of the derrick is in progress.
In addition, testing has begun on some of the installed rig equipment.
Construction is scheduled for completion in the third quarter
of 2003, after which the rig will be inaugurated.
The contract for DSS-20 was
awarded in February 2001. Agreements have been signed between
ExxonMobil subsidiary Exxon Azerbaijan Operating Company, LLC
(Exxon Azerbaijan), Chevron Overseas Petroleum Azerbaijan Limited,
Maersk Contractors and the State Oil Company of Azerbaijan Republic
(SOCAR) for use of the rig. Exxon's project at Zafar-Mashal is
at the top of the list to be the first well to be drilled.
About 800 Azerbaijani workers are currently involved with the
construction of modules at the Caspian Shipyard Company (CSC),
which is a joint venture of SOCAR, Keppel FELS and LUKOIL. Approximately
1,000 people will be employed at the peak of the construction
process.
ExxonMobil has been active in Azerbaijan
since 1995. Through subsidiaries the company holds interests
in four projects: Azeri-Chirag-Gunashli, Alov-Araz-Sharg, Zafar-Mashal,
and Nakhchivan and Oguz projects.
Back to Index AI 11.1 (Spring