Azeri-Chirag-Gunashli
(ACG) contract signed |
Sept1994 |
Chirag
development drilling |
August
1997 |
Chirag
First Oil |
November
1997 |
Supsa
pipeline operational |
February
1999 |
Water
injection project |
1999 |
Chirag drilling
technology upgraded |
2000 |
ACG Phase 1 Full
Field Development |
August 2001 |
Azeri subsea
drilling template |
June 2002 |
ACG Phase 2 Full
Field Development |
Sept 2002 |
Chirag and Sangachal
Terminal upgrade |
March 2003 |
Chirag
- 200 million barrels |
May
2003 |
West
Azeri template installed |
May
2003 |
Central
Azeri Living Quarters arrive in Baku |
July
2003 |
Central
Azeri drilling modules arrive in Baku |
Sept
2003 |
Central
Azeri jacket completed |
December
2003 |
Central Azeri
drilling modules arrive in Baku |
February 2004 |
Central Azeri
jacket completed |
March 2004 |
East Azeri Pre-Drilling
Program begins |
June 2004 |
Central Azeri
Gas pipeline installed and platform launched |
July 2004 |
Chirag - 250
million barrels |
August 2004 |
West
Azeri Platform drilling modules arrive in Baku |
August
2004 |
Central
Azeri Production, Drilling and Quarters Platform installed |
October
2004 |
Central
Azeri Production starts |
February
2005 |
Azeri
oil export starts |
March
2005 |
West
Azeri production, drilling and quarters platform launched |
May
2005 |
Central Azeri
casing-head gas delivered |
May 2005 |
Chirag - 300
million barrels |
June 2005 |
East Azeri drilling
modules and quarters platform arrive in Baku |
June 2005 |
Central Azeri
C&WP platform topsides launched |
July 2005 |
West Azeri topsides
installed |
Sept 2005 |
Deepwater
Gunashli Pre-Drilling Program starts |
December
2005 |
West
Azeri production starts |
January
2006 |
East
Azeri platform launched |
March
2006 |
C&WP
injects first gas |
May
2006 |
Deep-water
Gunashli drilling modules and quarters in Baku |
June
2006 |
East
Azeri topsides installed |
July
2006 |
East
Azeri production began |
October
2006 |